Smithbridge Road Project
Project Overview
The Smithbridge Road Project remains an ongoing collaborative effort involving the district, Concord Township, State Representative Craig Williams, and Senator John Kane. As part of this partnership, we are working in tandem with the district's renovation project. To recap, our joint efforts entail:
Turning Lanes: Installing turning lanes into the high school for improved traffic flow and safety.
Sidewalks: Constructing sidewalks from the front entrance of the high school down the length of Smithbridge Road, extending all the way to the Rachel Kohl Library. This addition promotes pedestrian safety and accessibility.
Traffic Circle: Creating a traffic circle at the intersection of Kirk and Temple Roads to enhance traffic management and safety in the area.
This collaborative approach underscores our commitment to addressing traffic and safety concerns in the community while also improving the overall infrastructure and accessibility in the vicinity of the school. We will continue to work diligently to ensure the success of the Smithbridge Road Project.
Project Timeline
The project unfolds through several distinct phases, each with its own timeline:
Design Phase
Schematic Design: April 2023 – July 2023
Design Development: July 2023 – November 2023
Construction Documents: November 2023 – February 2024
Permitting Phase
Concord Township Approvals: May 2023 – October 2023
Delaware County Conservation District Approvals: August 2023 – July 2024
Bidding Phase
Bidding: June 2024 – August 2024
Construction Phase
Construction: August 2024 – August 2025
This timeline provides a comprehensive overview of the project's progression, from initial design to completion, ensuring transparency and understanding of the project's trajectory.